Case Study 19: Austin Energy's Billing System Can't Light Up

10:39 Amrie 5 Comments

Austin's Energy's Billing System Can't Light Up


Question 1:

Is Austin Business Project is a failure?

Answer

Yes, the Austin Business Project is failure because:

Modernization billing project delays
  • Austin and IBM project late completion, delay schedule, software bugs
  • Complexity new billing system with 73 different interfaces

Software bugs
  • Error of thousands of bills
  • 65000 never received bills
  • 35000 in accurate bills, overcharging


Instability issues
  • Seriously impact business and customer
  • Persistent system error from billing department
  • Revenue loses


Customer services employee
  • Employee response one to one assistant for account accessing and correcting error.
  • Called themselves as alpha tester


Customer
  • Unable to access system online portal
  • System causes a lot of problem, not friendly and hard time for customer.


IBM failure
  • Billing software system failure


Question 2:

Describe the business impact of the faltering Austin Energy project.

Answer


Operation
  • Mostly affected is billing department.
  • Difficulties of issuing bills because of billing software failure.
  • Common error of customer not received bills, customer receive in accurate bills, account automatically cancelled.
  • Incurred more cots in utilities and operation. Since business function is interconnected, one function failure gives impact of another function such as production.
  • Business service is inaccurate, it give impact in revenue and profit even though they don’t have pressure of competitor.


Customer service
  • The department mostly affected.
  • Employee work in high level of stress.
  • Extra effort need to solve customer problem. They still need to serve customer better even though customer angry to show their disappointment towards the company.
  • Employee also treated in the same way as usual, do not receive any appreciation from the company.
  • Give impact of public relationship disaster.


Sales and marketing
  • Company also faced difficulties in determining the actual sales since the system leads more error.
  • Sales and profit decreasing.
  • Company might face law suit for this issues. If it is happening, more cost to handle legal costs. It is bad for company since give negative impact in their legacy.
  • Company also incurred more cost in advertising to give explanation to the public about what happen.


Finance and accounting
  • Inaccurate financial report since the actual value of revenue and profit inaccurate recorded.
  • Give impact of financial planning and investment.
  • The project is delayed, suppose fully operational in early 2011 but it still not fully operational and incurred more cost.
  • Management
  • Wrong decision making of having IBM to develop the software as the bad experience IBM performance in inventory management.
  • The service given by IBM is bad and disappointment.
  • Need to train all employees with new technology.


Customer
  • Mostly affected. 
  • System also not user friendly, Austin portal also always have problem, customer cant access account information.
  • Company also doesn’t think of their preference such as ability to choose time of the month that customer prefers to pay bills.


Question 3:

To what degree was IBM responsible for the problem countered by the Austin Energy billing project?

  • IBM not really responsive to the problems.
  • It made Austin Energy appealed so many times to IBM officials ranging from the managers of billing system project up to IBM CEO.
  • IBM responsible in find the roof of problem, make system correction, test the latest system version and implement the system.


Was Austin Energy at a fault for the problems? Explain your answer
  • Yes, Austin Energy is at fault for the problem. It is because:
  • Austin Energy as a user had to be committed to the system.
  • Probably, Austin Energy did not plan very properly in the project to develop the billing system.
  • They must have clear and proper project management objective which should deal with five major variables: scope, time, cost, quality and risk.
  • The agreement should clearly define the roles and responsibilities of both parties.


Question 4:

What were the specific organizational or technical factors as well as management factors involve in this project failure?

Answer

Organizational
  • Employee could not be committed enough and described as if they are alpha tester when they encountered bugs and issues that never have made it to a live version.
  • Unable to meet customer satisfaction.
  • No realignment internally and externally.
  • Caused vastly on costs that exceed budgets.
  • Fail to meet customer expectation.
  • Lost trust draws customer away.


Technical
  • No specific infrastructure.
  • Unreliable system caused money loss.
  • Did not work closely with third party vendors like oracle.
  • Customers unable to access the system’s online portal.


Management
  • No strategy which cause time slippage.
  • No business solutions.
  • Interrelated with manpower.
  • Repeating mistakes and delays.
  • Improper project management objective.


Question 5:

Describe the steps Austin Energy and IBM should have taken to better manage this project.

Answer

Austin Energy and IBM need to develop an information system plan which indicates:

The direction of system development
  • Overview of plant contents
  • Current and future business organization
  • Key biz process
  • Management strategy


The rationale
  • Current situation and current business organization
  • Changing environment
  • Major goals of the biz plan
  • Firm’s strategic plan


The current systems / situation
  • Major system supporting biz function and process
  • Current infrastructure capabilities
  • Difficulties meeting business requirement
  • Anticipated future demand


New developments to consider
  • New system project
  • New infrastructure capabilities required


The management strategy
  • Acquisition plan
  • Milestone and timing
  • Organizational realignment
  • Management control


The implementation plan
  • Anticipated difficulties in implementation
  • Progress report
  • Budget requirement
  • Requirement
  • Potential saving
  • Financing
  • Acquisition cycle

5 comments:

  1. Your Affiliate Money Printing Machine is waiting -

    Plus, earning money online using it is as simple as 1--2--3!

    Here are the steps to make it work...

    STEP 1. Input into the system what affiliate products the system will advertise
    STEP 2. Add PUSH BUTTON traffic (this LITERALLY takes 2 minutes)
    STEP 3. Watch the system explode your list and sell your affiliate products all by itself!

    So, do you want to start making profits?

    Click here to check it out

    ReplyDelete

  2. IEEE Final Year projects Project Center in Chennai are consistently sought after. Final Year Students Projects take a shot at them to improve their aptitudes, while specialists like the enjoyment in interfering with innovation. For experts, it's an alternate ball game through and through. Smaller than expected IEEE Final Year project centers ground for all fragments of CSE & IT engineers hoping to assemble. <Final Year Projects for CSE It gives you tips and rules that is progressively critical to consider while choosing any final year project point.

    JavaScript Training in Chennai

    JavaScript Training in Chennai

    The Angular Training covers a wide range of topics including Components, project projects for cseAngular Directives, Angular Services, Pipes, security fundamentals, Routing, and Angular programmability. The new Angular TRaining will lay the foundation you need to specialise in Single Page Application developer. Angular Training

    ReplyDelete
  3. The blog was absolutely fantastic! Lot of great information which can be helpful in some or the other way. Keep updating the blog. Inventory Management Software

    ReplyDelete